I asked, “Why do you need this kind of report?’
They shared the purpose of developing this report – ‘Order-wise total worked hours.’
1. They need the report to compare the projected working hours to complete an order and the actual hours worked to complete the order by the production lines.
2. This comparison would help to know how much extra cost is incurred in completing an order (in the stitching area). The labor costs are estimated before moving the order in a line vs actual expenses on the order.
3. The variation ratio would be used in calculating labor costs in future orders with better accuracy
4. Another important purpose of this is industrial engineers who estimate projected order completion hours, can improve their projection by looking into the variation of their current estimates and considering the different variables of order completion.
How to make the report for total hours worked by orders
The report can be developed easily if the factory keeps their daily manpower record by style and by a line and daily working hours. Records of OT working hours (if applicable).
Last day hours worked (B)= Manpower x hours worked
Total hours worked on the other day (C)= Manpower x 8 x Number of days
Order wise total hours = A+B+C

Variable in establishing a formula for calculating total hours worked
- Many operators will not be working a full day (8 hours) on the same order
- Many operators in a line will have no work (idle time) all day and many loss time hours will be there every day. Do you like to include all these idle hours? From the cost perspective, yes, you should. But from the performance perspective, you should not.
- Operators will be moved from one line to another (one order to another order)
- Few operators will be helping on the said order to build up WIP or complete the high WIP. Can you keep a record for the dynamic nature of workers’ movement in the production lines?
- You will have absentees on some days and on some other days line will not perform well.
Manually preparing daily records with all these variables is not practical. Then how one can make such a report and get complete working hours on the orders?