What is line planning?
During booking orders or allocating orders to the production line, planners must check what is running on the line and how many days it will take to complete the running style.
Benefits of Line planning
Table-1: Line Plan
|
|
Line 1
|
Line 2
|
Total
|
||
|
Date
|
Daily
Prod. |
Cum
Prod. |
Daily
Prod. |
Cum
Prod. |
Daily
Prod. |
|
1-Dec
|
loading #2341A,
Qty -3000 pieces |
300
|
1200
|
300
|
|
|
2-Dec
|
200
|
200
|
300
|
1500
|
500
|
|
3-Dec
|
250
|
450
|
300
|
1800
|
550
|
|
4-Dec
|
400
|
850
|
200
|
2000
|
600
|
|
5-Dec
|
400
|
1250
|
loading #Polo ,
Qty -1500 pieces |
400
|
|
|
6-Dec
|
400
|
1650
|
0
|
0
|
400
|
|
7-Dec
|
400
|
2050
|
100
|
100
|
500
|
|
8-Dec
|
400
|
2450
|
300
|
400
|
700
|
|
9-Dec
|
400
|
2850
|
350
|
750
|
750
|
|
10-Dec
|
150
|
3000
|
350
|
1100
|
500
|
|
11-Dec
|
loading #432K,
Qty -5500 pieces |
400
|
1500
|
400
|
|
|
12-Dec
|
100
|
100
|
loading #YK45,
Qty -4500 pieces |
100
|
|
|
13-Dec
|
250
|
350
|
200
|
200
|
450
|
|
14-Dec
|
500
|
850
|
250
|
450
|
750
|
|
15-Dec
|
500
|
1350
|
400
|
850
|
900
|
|
16-Dec
|
500
|
1850
|
400
|
1250
|
900
|
|
17-Dec
|
500
|
2350
|
400
|
1650
|
900
|
|
18-Dec
|
500
|
2850
|
400
|
2050
|
900
|
|
19-Dec
|
500
|
3350
|
400
|
2450
|
900
|
|
20-Dec
|
500
|
3850
|
400
|
2850
|
900
|
|
21-Dec
|
500
|
4350
|
400
|
3250
|
900
|
|
22-Dec
|
500
|
4850
|
400
|
3650
|
900
|
|
23-Dec
|
150
|
5000
|
400
|
4050
|
550
|
|
Daily Prod. – Daily production or
line output
Cum Prod. – Cumulative production
of the style to date |
|||||
How to calculate the production capacity of a factory?